WAT26-COT01
Five villages, West and East
Borehole, 5 m³ water tower, standpipes and management committee in five villages. Works planned October 2026 to January 2027.
In preparation
- Area
- West and East of Côte d’Ivoire
- Period
- October 2026 to January 2027
- Villages
- 5
- Inhabitants concerned
- 19,258
- Facilities per village
- Borehole, 5 m³ water tower, standpipes, management committee
The villages
Kpangouine (2,513 inhabitants), Le Cavally (1,875), Sanguéhi (8,000), Assindi (2,000) and Nagafou (4,870).
What is planned
In each village: a borehole, a 5 m³ water tower, standpipes and a management committee of 8 trained members, at least 40% women, with a maintenance fund. Works are planned from October 2026 to January 2027.
Project documents
Reports for this project will be published after review.